Coal Plant Efficiency & Decarbonisation Programme

  Group ESG Lead
Lifecycle Stage
1. Discover2. Triage3. Design4. Approve5. Deliver6. Verify7. Embed, Scale or Close
Stage Gates
  • Baseline Approval
    Head of Sustainability, SPG · 2025-01-15
    Baseline data verified against CEMS records
    Approved
  • Business Case Approval
    CFO, SPG · 2025-02-10
    Approved within FY25 capital plan
    Approved
  • Technical Review
    Chief Engineer, SPG · 2025-03-01
    Approved
  • Funding Approval
    Group Capital Committee · 2025-03-20
    Approved
  • Evidence Review
    Group ESG Lead ·
    Awaiting Q2 monitoring data
    In Review
  • Claim Approval
    Pending
Milestones
MilestoneOwnerDueStatus
Complete combustion optimisation studyPlant Engineering Manager2025-06-30Complete
Install upgraded burners Unit 1Chief Engineer, SPG2026-03-31In Progress
Install upgraded burners Unit 2Chief Engineer, SPG2026-09-30Not Started
Verify emissions intensity reductionGroup ESG Lead2027-06-30Not Started
Measurement (Metrics)
MetricCategoryUnit
Scope 1 GHG Emissions IntensityoutcometCO2e/MWh
Plant Heat RateoutputkJ/kWh
Add Metric
Evidence
EvidenceTypeStatus
CEMS Q1 2025 Data Exportsource-system extractApproved
Combustion Optimisation Study Reportmonitoring reportApproved
Attach Evidence
Updates, Decisions & Comments
status
Combustion optimisation study complete; results confirm 4% heat rate improvement is achievable
Plant Engineering Manager · 2026-07-06 01:44:16
risk
Supply chain delay risk identified for burner components - alternative supplier being sourced
Plant Engineering Manager · 2026-07-06 01:44:16